- Cronograma Nueva Sede

Anuncio
ID
Task
Mode
Task Name
Duration
Start
Finish
Predecessors3rd Quarter
Oct '15
1
2
Cronograma Nueva Sede
673 days
Mon 09/12/16
Wed 04/10/19
3
Selección de Terreno
90 days
Mon 09/12/16
Mon 01/16/17
Identificación de terrenos 90 days
nacionales
Verificar terrenos
25 days
disponibles en ANATI
Verificar derechos
10 days
pocesorios (Municipio,
ANATI, Reforma Agraria,
Corregiduría)
Mon 09/12/16
Mon 01/16/17
Mon 09/12/16
Mon 10/17/16
6SF
Mon 10/17/16
Mon 10/31/16
7SF
4
5
6
7
1st Quarter
3rd Quarter
Jan '16 Apr '16
Jul '16
Oct '16
1st Quarter
Jan '17 Apr '17
3rd Quarter
Jul '17
Oct '17
1st Quarter
3rd Quarter
Jan '18 Apr '18
Jul '18
Oct '18
Verificar terrenos disponibles en ANATI
Verificar derechos pocesorios (Municipio, ANATI, Reforma Agraria, Corregiduría)
10/31
0 days
Mon 10/31/16
Mon 10/31/16
8SF
8
Determinar si el terreno
está ocupado
Aprobación de la UABR
44 days
Mon 10/31/16
Fri 12/30/16
9SF
Aprobación de la UABR
9
Traspaso del Terreno
11 days
Fri 12/30/16
Mon 01/16/17
12SF
Traspaso del Terreno
10
373 days
Tue 11/15/16
Thu 04/19/18
44 days
Tue 11/15/16
Mon 01/16/17
12SF
Elaboración de pliegos y especificaciones
12
Licitación de diseño y
construcción
Elaboración de pliegos y
especificaciones
Publicación
0 days
Mon 01/16/17
Mon 01/16/17
13
Periodo de Licitación
20 days
Mon 01/16/17
Fri 02/10/17
12
14
Presentación de Propuesta 0 days
Fri 02/10/17
Fri 02/10/17
13
02/10
15
Evaluación
10 days
Mon 02/13/17
Fri 02/24/17
14
Evaluación
16
Adjudicación
0 days
Fri 02/24/17
Fri 02/24/17
15
02/24
17
Periodo para Impugnación y 5 days
Presentación de Fianza
Mon 02/27/17
Fri 03/03/17
16
Periodo para Impugnación y Presentación de Fianza
18
Firma del Contrato
0 days
Fri 03/03/17
Fri 03/03/17
17
19
Refrendo de Contraloría
30 days
Mon 03/06/17
Fri 04/14/17
18
20
Orden de Proceder
0 days
Fri 04/14/17
Fri 04/14/17
19
11
Project: Cronograma Nueva Se
Date: Wed 03/09/16
1st Quarter
3rd Quarter
Jan '19 Apr '19 Jul '19
Oct '19
01/16
Periodo de Licitación
03/03
Refrendo de Contraloría
04/14
Task
Inactive Task
Manual Summary Rollup
External Milestone
Progress
Split
Inactive Milestone
Manual Summary
Deadline
Manual Progress
Milestone
Inactive Summary
Start-only
Path Predecessor Milestone Task
Summary
Manual Task
Finish-only
Path Predecessor Summary Task
Project Summary
Duration-only
External Tasks
Path Predecessor Normal Task
Page 1
1st Quarter
Jan '20
ID
Task
Mode
Task Name
Duration
Start
Finish
Predecessors3rd Quarter
Oct '15
21
Diseño Preliminar
22 days
Mon 04/17/17
Tue 05/16/17
20
22
66 days
Wed 05/17/17
Wed 08/16/17
21
23
Estudio de Impacto
Ambiental
Aprobación de EIA
110 days
Thu 08/17/17
Wed 01/17/18
22
24
Diseño
88 days
Thu 08/17/17
Mon 12/18/17
22
25
Aprobaciones
88 days
Tue 12/19/17
Thu 04/19/18
22,21,24
254 days
Fri 04/20/18
Wed 04/10/19
26
Obra Civil
1st Quarter
3rd Quarter
Jan '16 Apr '16
Jul '16
Oct '16
1st Quarter
Jan '17 Apr '17
3rd Quarter
Jul '17
Oct '17
Diseño Preliminar
1st Quarter
3rd Quarter
Jan '18 Apr '18
Jul '18
Oct '18
1st Quarter
3rd Quarter
Jan '19 Apr '19 Jul '19
Oct '19
Estudio de Impacto Ambiental
Aprobación de EIA
Diseño
Aprobaciones
Actividades Preliminares
27
Actividades Preliminares
11 days
Fri 04/20/18
Fri 05/04/18
23,25
28
Fundaciones
35 days
Mon 05/07/18
Fri 06/22/18
27
29
Obra Civil
120 days
Mon 06/25/18
Fri 12/07/18
28
30
Acabados
66 days
Mon 12/10/18
Mon 03/11/19
29
31
Mon 05/07/18
Tue 06/05/18
27
32
Drenaje Pluviales y
22 days
Sanitarios
Rampa y Estacionamientos 66 days
Mon 12/10/18
Mon 03/11/19
29
33
Agua Potable
15 days
Mon 12/10/18
Fri 12/28/18
29
Agua Potable
34
Electricidad
22 days
Mon 12/10/18
Tue 01/08/19
29
Electricidad
35
Pruebas Finales
22 days
Tue 03/12/19
Wed 04/10/19
30
36
Aceptación Final
0 days
Wed 04/10/19
Wed 04/10/19
35
Project: Cronograma Nueva Se
Date: Wed 03/09/16
1st Quarter
Jan '20
Fundaciones
Obra Civil
Acabados
Drenaje Pluviales y Sanitarios
Rampa y Estacionamientos
Pruebas Finales
04/10
Task
Inactive Task
Manual Summary Rollup
External Milestone
Progress
Split
Inactive Milestone
Manual Summary
Deadline
Manual Progress
Milestone
Inactive Summary
Start-only
Path Predecessor Milestone Task
Summary
Manual Task
Finish-only
Path Predecessor Summary Task
Project Summary
Duration-only
External Tasks
Path Predecessor Normal Task
Page 2