ID Task Mode Task Name Duration Start Finish Predecessors3rd Quarter Oct '15 1 2 Cronograma Nueva Sede 673 days Mon 09/12/16 Wed 04/10/19 3 Selección de Terreno 90 days Mon 09/12/16 Mon 01/16/17 Identificación de terrenos 90 days nacionales Verificar terrenos 25 days disponibles en ANATI Verificar derechos 10 days pocesorios (Municipio, ANATI, Reforma Agraria, Corregiduría) Mon 09/12/16 Mon 01/16/17 Mon 09/12/16 Mon 10/17/16 6SF Mon 10/17/16 Mon 10/31/16 7SF 4 5 6 7 1st Quarter 3rd Quarter Jan '16 Apr '16 Jul '16 Oct '16 1st Quarter Jan '17 Apr '17 3rd Quarter Jul '17 Oct '17 1st Quarter 3rd Quarter Jan '18 Apr '18 Jul '18 Oct '18 Verificar terrenos disponibles en ANATI Verificar derechos pocesorios (Municipio, ANATI, Reforma Agraria, Corregiduría) 10/31 0 days Mon 10/31/16 Mon 10/31/16 8SF 8 Determinar si el terreno está ocupado Aprobación de la UABR 44 days Mon 10/31/16 Fri 12/30/16 9SF Aprobación de la UABR 9 Traspaso del Terreno 11 days Fri 12/30/16 Mon 01/16/17 12SF Traspaso del Terreno 10 373 days Tue 11/15/16 Thu 04/19/18 44 days Tue 11/15/16 Mon 01/16/17 12SF Elaboración de pliegos y especificaciones 12 Licitación de diseño y construcción Elaboración de pliegos y especificaciones Publicación 0 days Mon 01/16/17 Mon 01/16/17 13 Periodo de Licitación 20 days Mon 01/16/17 Fri 02/10/17 12 14 Presentación de Propuesta 0 days Fri 02/10/17 Fri 02/10/17 13 02/10 15 Evaluación 10 days Mon 02/13/17 Fri 02/24/17 14 Evaluación 16 Adjudicación 0 days Fri 02/24/17 Fri 02/24/17 15 02/24 17 Periodo para Impugnación y 5 days Presentación de Fianza Mon 02/27/17 Fri 03/03/17 16 Periodo para Impugnación y Presentación de Fianza 18 Firma del Contrato 0 days Fri 03/03/17 Fri 03/03/17 17 19 Refrendo de Contraloría 30 days Mon 03/06/17 Fri 04/14/17 18 20 Orden de Proceder 0 days Fri 04/14/17 Fri 04/14/17 19 11 Project: Cronograma Nueva Se Date: Wed 03/09/16 1st Quarter 3rd Quarter Jan '19 Apr '19 Jul '19 Oct '19 01/16 Periodo de Licitación 03/03 Refrendo de Contraloría 04/14 Task Inactive Task Manual Summary Rollup External Milestone Progress Split Inactive Milestone Manual Summary Deadline Manual Progress Milestone Inactive Summary Start-only Path Predecessor Milestone Task Summary Manual Task Finish-only Path Predecessor Summary Task Project Summary Duration-only External Tasks Path Predecessor Normal Task Page 1 1st Quarter Jan '20 ID Task Mode Task Name Duration Start Finish Predecessors3rd Quarter Oct '15 21 Diseño Preliminar 22 days Mon 04/17/17 Tue 05/16/17 20 22 66 days Wed 05/17/17 Wed 08/16/17 21 23 Estudio de Impacto Ambiental Aprobación de EIA 110 days Thu 08/17/17 Wed 01/17/18 22 24 Diseño 88 days Thu 08/17/17 Mon 12/18/17 22 25 Aprobaciones 88 days Tue 12/19/17 Thu 04/19/18 22,21,24 254 days Fri 04/20/18 Wed 04/10/19 26 Obra Civil 1st Quarter 3rd Quarter Jan '16 Apr '16 Jul '16 Oct '16 1st Quarter Jan '17 Apr '17 3rd Quarter Jul '17 Oct '17 Diseño Preliminar 1st Quarter 3rd Quarter Jan '18 Apr '18 Jul '18 Oct '18 1st Quarter 3rd Quarter Jan '19 Apr '19 Jul '19 Oct '19 Estudio de Impacto Ambiental Aprobación de EIA Diseño Aprobaciones Actividades Preliminares 27 Actividades Preliminares 11 days Fri 04/20/18 Fri 05/04/18 23,25 28 Fundaciones 35 days Mon 05/07/18 Fri 06/22/18 27 29 Obra Civil 120 days Mon 06/25/18 Fri 12/07/18 28 30 Acabados 66 days Mon 12/10/18 Mon 03/11/19 29 31 Mon 05/07/18 Tue 06/05/18 27 32 Drenaje Pluviales y 22 days Sanitarios Rampa y Estacionamientos 66 days Mon 12/10/18 Mon 03/11/19 29 33 Agua Potable 15 days Mon 12/10/18 Fri 12/28/18 29 Agua Potable 34 Electricidad 22 days Mon 12/10/18 Tue 01/08/19 29 Electricidad 35 Pruebas Finales 22 days Tue 03/12/19 Wed 04/10/19 30 36 Aceptación Final 0 days Wed 04/10/19 Wed 04/10/19 35 Project: Cronograma Nueva Se Date: Wed 03/09/16 1st Quarter Jan '20 Fundaciones Obra Civil Acabados Drenaje Pluviales y Sanitarios Rampa y Estacionamientos Pruebas Finales 04/10 Task Inactive Task Manual Summary Rollup External Milestone Progress Split Inactive Milestone Manual Summary Deadline Manual Progress Milestone Inactive Summary Start-only Path Predecessor Milestone Task Summary Manual Task Finish-only Path Predecessor Summary Task Project Summary Duration-only External Tasks Path Predecessor Normal Task Page 2