PRESUPUESTO DE OBRA PROYECTO : PROPIETARIO : UBICACION : FECHA PROYECTO : Item Descripción 1 MOVIMIENTO DE TIERRA Unid. Cant. Precio Parcial Sub Total 538,416.77 1.1 EXCAV. ZANJAS Y ZAPATAS h=1,50 m. m³ 9,567.00 34.88 333,696.96 1.2 RELLENO CON MATERIAL SELECIONADO m³ 7,568.20 27.05 204,719.81 2 2.1 OBRAS DE CONCRETO ARMADO 1,166,560.58 OBRAS DE CONCRETO ARMADO EN ZAPATAS 340,453.93 2.1.1 ENCOFRADO Y DESENCOFRADO m² 2,065.23 49.21 101,629.97 2.1.2 ACERO f'y =4200 KG/CM2, GRADO 60 kg 3,594.60 11.53 41,445.74 CONCRETO F'C= 245 KG/CM2. 2.1.3 3.1 3.1.1 3.1.2 3.1.3 4.1 m³ 434.84 453.91 197,378.22 ENCOFRADO Y DESENCOFRADO m² 2,574.65 66.32 170,750.79 ACERO f'y =4200 KG/CM2, GRADO 60 kg 3,748.12 13.89 52,061.39 CONCRETO F'C= 245 KG/CM2. m³ 376.80 438.72 165,309.70 OBRAS DE CONCRETO ARMADO EN COLUMNAS 388,121.87 OBRAS DE CONCRETO ARMADO EN VIGA 437,984.78 4.1.1 ENCOFRADO Y DESENCOFRADO m² 2,696.60 74.37 200,546.14 4.1.2 ACERO f'y =4200 KG/CM2, GRADO 60 kg 3,864.85 14.75 57,006.54 4.1.3 CONCRETO F'C= 245 KG/CM2. m³ 394.62 457.23 180,432.10 ARQUITECTURA 97,037.62 MURO DE ALBAÑILERIA CONFINADA m² ASENTADO DE LADRILLO KING KONG 18H APAREJO SOGA m² 548.96 42.54 23,352.76 ASENTADO DE LADRILLO KING KONG 18H APAREJO CABEZA m² 494.64 51.97 25,706.44 3 TARRAJEO EN MUROS m² 1,043.60 23.21 24,221.96 3.1 PUERTA CORTAFUEGO m² 42.00 565.63 23,756.46 TABLERO ELECTRICO METALICO und 153.00 385.62 58,999.86 POZO A TIERRA und 17.00 782.17 13,296.89 glb 20.00 858.12 17,162.40 3.2 97,037.62 INSTALACIONES ELECTRICAS 89,459.15 PRUEBAS ELECTRICAS Costo Directo 1,891,474.12 Gastos Generales 7.80% Utilidad 5.00% 147,534.98 94,573.71 Sub Total 2,133,582.81 IGV 384,044.91 Presupuesto de Obra 2,517,627.72 K= a*(Jr/Jo) +b*(ACCr/ACCo) +c*(AGr/AGo) +d*(MAHr/MAHo) +e*(GGUr/GGo) = 1 SIMB. J AFA H DESCRIPCIÓN mano de obra inc. Leyes sociales Acero de const. Liso acero de const. Corrifo cemento portland v cerrajeria importada agregado grueso maq. Y qeuip. Import. AG I AGRUP. COEF. INC. % 2 3 4 5 6 0.4160 100.00% 650.44 650.44 653.54 653.54 11.72% 821.06 96.23 812.99 95.28 19.03% 831.00 158.14 794.85 151.26 0.1840 66.74% 482.08 321.74 465.23 310.49 0.0070 2.50% 286.45 1 47 0.4160 2 0.0320 3 0.0520 Ir Enero 2022 Io Noviembre 2021 Ir/Io K 7 (1)*(7) 1.00 0.414 1.03 0.284 1.00 0.069 0.275 23 24 7.16 583.27 280.76 7.02 564.06 5 0.0290 42.10% 611.95 257.63 601 253.02 49 0.0020 3.44% 396.02 13.62 403.22 13.87 bloque y ladrillo artefacto alumbrado interrior artefacto alumbrado interrior 17 0.0110 16.02% 965.84 154.73 950.97 152.35 0.0690 12 0.0170 24.63% 339.71 83.67 346.94 85.45 19 0.0090 13.81% 1225.76 1238.42 madera tornillo 43 0.0860 67.95% 858.93 169.28 678.93 583.64 843.51 171.03 675.71 573.17 maq. Y qeuip. Nacional 48 0.0070 5.27% 395.47 20.84 396.32 20.89 4 0.0200 15.96% 615.03 98.16 613.13 97.86 37 73 0.013 0.001 10.20% 0.62% 381.3 882.27 38.89 5.47 726.16 383.63 892.23 39.13 5.53 715.68 1.01 0.128 496.00 1.01 0.115 agregado fino herrramientas manuales ducto telefonico GGU COEF.INCID. I.U Indice greal. Preciso cons. 39 0.1140 1.0000 0.126 0.114 100.00% 500.07 500.07 496 K= 1.011 VALORIZACION DE OBRA Nº 01 Mar-22 OBRA : CONTRATISTA : RESIDENTE SUPERVISOR PERIODO MONTO PRESUP. BASE : MONTO CONTRATADO : SISTEMA DE CONTRATACION: : FECHA PRESUP. BASE : FORMA DE EJECUCION: FORMULA Nº 01 - ESTRUCTURAS PRESUPUESTO BASE ITEM DESCRIPCION UND MET. P. UNIT. 1 MOVIMIENTO DE TIERRA 1.1 EXCAV. ZANJAS Y ZAPATAS h=1,50 m. m³ 9,567.00 34.88 1.2 RELLENO CON MATERIAL SELECIONADO m³ 7,568.20 27.05 AVANCE ANTERIOR P. TOTAL MET. MONTO S/. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 MONTO S/ % AVANCE ACTUAL AVANCE ACUMUL. MET. MONTO S/. % AVANCE ACUMUL. SALDO MET. MONTO % POR VAL. 72.07% 6895.00 240497.60 72.07% 2672.00 93199.36 168656.75 82.38% 6235.00 168656.75 82.38% 1333.20 36063.06 98469.21 34728.36 70809.96 96.89% 83.79% 35.88% 2001.00 3012.00 156.00 98469.21 34728.36 70809.96 96.89% 83.79% 35.88% 64.23 582.60 278.84 3160.76 6717.38 126568.26 3.11% 16.21% 64.12% 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 0.00% 0.00% 2574.65 3748.12 376.80 170750.79 52061.39 165309.70 100.00% 100.00% 100.00% 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 0.00% 0.00% 2696.60 3864.85 394.62 200546.14 57006.54 180432.10 100.00% 100.00% 100.00% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 548.96 494.64 1043.60 42.00 23352.76 25706.44 24221.96 23756.46 100.00% 100.00% 100.00% 100.00% 17162.4 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 0.00% 0.00% 153.00 17.00 20.00 58999.86 13296.89 17162.40 100.00% 100.00% 100.00% 1,891,474.12 156,992.35 138,077.61 2,186,544.08 2,186,544.08 393,577.93 2,580,122.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 204719.81 2 OBRAS DE CONCRETO ARMADO 2.1 OBRAS DE CONCRETO ARMADO EN ZAPATAS 2.1.1 ENCOFRADO Y DESENCOFRADO m² 2,065.23 2.1.2 ACERO f'y =4200 KG/CM2, GRADO 60 kg 3,594.60 11.53 41445.738 2.1.3 CONCRETO F'C= 245 KG/CM2. m³ 434.84 453.91 197378.2244 3.1 OBRAS DE CONCRETO ARMADO EN COLUMNAS 3.1.1 ENCOFRADO Y DESENCOFRADO m² 2,574.65 66.32 170750.788 3.1.2 ACERO f'y =4200 KG/CM2, GRADO 60 kg 3,748.12 13.89 52061.3868 3.1.3 CONCRETO F'C= 245 KG/CM2. m³ 376.80 438.72 165309.696 4.1 OBRAS DE CONCRETO ARMADO EN VIGA 4.1.1 ENCOFRADO Y DESENCOFRADO m² 2,696.60 4.1.2 ACERO f'y =4200 KG/CM2, GRADO 60 kg 3,864.85 14.75 57006.5375 4.1.3 CONCRETO F'C= 245 KG/CM2. m³ 394.62 457.23 180432.1026 548.96 42.54 23352.7584 74.37 MET. 240497.60 333696.96 49.21 AVANCE ACTUAL % 101629.9683 200546.142 6895 6235 2001.00 3012.00 156.00 27.93% 17.62% ARQUITECTURA MURO DE ALBAÑILERIA CONFINADA m² ASENTADO DE LADRILLO KING KONG 18H APAREJO SOGA m² ASENTADO DE LADRILLO KING KONG 18H APAREJO CABEZA m² 494.64 51.97 25706.4408 3 TARRAJEO EN MUROS m² 1,043.60 23.21 24221.956 3.1 PUERTA CORTAFUEGO m² 42.00 565.63 23756.46 3.2 INSTALACIONES ELECTRICAS TABLERO ELECTRICO METALICO und 153.00 385.62 POZO A TIERRA und 17.00 782.17 PRUEBAS ELECTRICAS glb 20.00 858.12 COSTO DIRECTO GASTOS GENERALES UTILIDAD SUB TOTAL 8.30% 7.30% 1.0000 18.00% IMPUESTO (IGV) TOTAL PRESUPUESTO CONTRATADO PORCENTAJE DE AVANCE (%) 58999.86 13296.89 100.00% 0.00% 613,161.88 50,892.44 44,760.82 708,815.14 708,815.14 127,586.73 836,401.87 32.42% 613,161.88 50,892.44 44,760.82 708,815.14 708,815.14 127,586.73 836,401.87 1,278,312.24 106,099.91 93,316.79 1,477,728.94 1,477,728.94 265,991.20 1,743,720.14 32.42% 67.58% VALORIZACION ENERO = S/ 836,401.87 R=V(K-1) = S/ 8,784.77 VR=V*K = S/ 845,186.64 VALORIZACION DE OBRA Nº 02 Mar-22 OBRA : CONTRATISTA : RESIDENTE SUPERVISOR MONTO PRESUP. BASE : MONTO CONTRATADO : SISTEMA DE CONTRATACION: : PERIODO FECHA PRESUP. BASE : FORMA DE EJECUCION: FORMULA Nº 01 - ESTRUCTURAS PRESUPUESTO BASE ITEM DESCRIPCION UND MET. P. UNIT. 1 MOVIMIENTO DE TIERRA 1.1 EXCAV. ZANJAS Y ZAPATAS h=1,50 m. m³ 9,567.00 34.88 1.2 RELLENO CON MATERIAL SELECIONADO m³ 7,568.20 27.05 AVANCE ANTERIOR P. TOTAL MONTO S/. MET. 333696.96 6895 204719.81 6235 2 OBRAS DE CONCRETO ARMADO 2.1 OBRAS DE CONCRETO ARMADO EN ZAPATAS 2.1.1 ENCOFRADO Y DESENCOFRADO m² 2,065.23 101629.9683 2001 2.1.2 ACERO f'y =4200 KG/CM2, GRADO 60 kg 3,594.60 11.53 41445.738 3012 2.1.3 CONCRETO F'C= 245 KG/CM2. m³ 434.84 453.91 197378.2244 156 3.1 OBRAS DE CONCRETO ARMADO EN COLUMNAS 3.1.1 ENCOFRADO Y DESENCOFRADO m² 2,574.65 66.32 170750.788 3.1.2 ACERO f'y =4200 KG/CM2, GRADO 60 kg 3,748.12 13.89 52061.3868 3.1.3 CONCRETO F'C= 245 KG/CM2. m³ 376.80 438.72 165309.696 4.1 OBRAS DE CONCRETO ARMADO EN VIGA 4.1.1 ENCOFRADO Y DESENCOFRADO m² 2,696.60 4.1.2 ACERO f'y =4200 KG/CM2, GRADO 60 kg 3,864.85 14.75 57006.5375 4.1.3 CONCRETO F'C= 245 KG/CM2. m³ 394.62 457.23 180432.1026 548.96 42.54 23352.7584 49.21 74.37 AVANCE ACTUAL % MET. 240497.60 72.07 168656.75 82.38 98469.21 34728.36 70809.96 96.89 83.79 35.88 0.00 0.00 0.00 200546.142 MONTO S/ % AVANCE ACTUAL m² ASENTADO DE LADRILLO KING KONG 18H APAREJO SOGA m² ASENTADO DE LADRILLO KING KONG 18H APAREJO CABEZA m² 494.64 51.97 25706.4408 3 TARRAJEO EN MUROS m² 1,043.60 23.21 24221.956 3.1 PUERTA CORTAFUEGO m² 42.00 565.63 23756.46 3.2 INSTALACIONES ELECTRICAS TABLERO ELECTRICO METALICO und 153.00 385.62 POZO A TIERRA und 17.00 782.17 PRUEBAS ELECTRICAS glb 20.00 858.12 COSTO DIRECTO GASTOS GENERALES UTILIDAD SUB TOTAL 8.30% 7.30% IMPUESTO (IGV) TOTAL PRESUPUESTO CONTRATADO 1.0000 18.00% PORCENTAJE DE AVANCE (%) % AVANCE ACUMUL. SALDO MET. % POR VAL. MONTO 27.93% 9567.00 333696.96 100.00% 0.00 0.00 17.62% 7568.20 204719.81 100.00% 0.00 0.00 3160.76 6717.38 19972.04 3.11% 16.21% 10.12% 2065.23 3594.60 200.00 101629.97 41445.74 90782.00 100.00% 100.00% 45.99% 0.00 0.00 234.84 0.00 0.00 106596.22 0.00% 0.00% 54.01% 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 0.00% 0.00% 2574.65 3748.12 376.80 170750.79 52061.39 165309.70 100.00% 100.00% 100.00% 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 2696.60 3864.85 394.62 200546.14 57006.54 180432.10 100.00% 100.00% 100.00% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 548.96 494.64 1043.60 42.00 23352.76 25706.44 24221.96 23756.46 100.00% 100.00% 100.00% 100.00% 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 0.00% 0.00% 153.00 17.00 20.00 58999.86 13296.89 17162.40 100.00% 100.00% 100.00% 17162.4 0.00 0.00 0.00 613,161.88 50,892.44 44,760.82 708,815.14 708,815.14 127,586.73 836,401.87 100.00% 32.42% 13296.89 S/. 36063.06 1,891,474.12 156,992.35 138,077.61 2,186,544.08 2,186,544.08 393,577.93 2,580,122.01 58999.86 MONTO 93199.36 2672 1333.2 64.23 582.60 44.00 ARQUITECTURA MURO DE ALBAÑILERIA CONFINADA AVANCE ACUMUL. MET. 159,112.60 13,206.35 11,615.22 183,934.17 183,934.17 33,108.15 217,042.32 772,274.48 64,098.78 56,376.04 892,749.30 892,749.30 160,694.87 1,053,444.17 8.41% 0.00% 0.00% 1,119,199.64 92,893.57 81,701.57 1,293,794.78 1,293,794.78 232,883.06 1,526,677.84 40.83% 59.17% VALORIZACION FEBRERO = S/ 217,042.32 R=V(K-1) = S/ 2,279.61 VR=V*K = S/ 219,321.93 VALORIZACION DE OBRA Nº 03 Mar-22 OBRA : CONTRATISTA : RESIDENTE SUPERVISOR PERIODO MONTO PRESUP. BASE : MONTO CONTRATADO : SISTEMA DE CONTRATACION: : FECHA PRESUP. BASE : FORMA DE EJECUCION: FORMULA Nº 01 - ESTRUCTURAS PRESUPUESTO BASE ITEM DESCRIPCION UND MET. P. UNIT. 1 MOVIMIENTO DE TIERRA 1.1 EXCAV. ZANJAS Y ZAPATAS h=1,50 m. m³ 9,567.00 34.88 1.2 RELLENO CON MATERIAL SELECIONADO m³ 7,568.20 27.05 AVANCE ANTERIOR P. TOTAL MET. 333696.96 9567.00 204719.81 7568.20 2 OBRAS DE CONCRETO ARMADO 2.1 OBRAS DE CONCRETO ARMADO EN ZAPATAS 2.1.1 ENCOFRADO Y DESENCOFRADO m² 2,065.23 101629.9683 2065.23 2.1.2 ACERO f'y =4200 KG/CM2, GRADO 60 kg 3,594.60 11.53 41445.738 3594.60 2.1.3 CONCRETO F'C= 245 KG/CM2. m³ 434.84 453.91 197378.2244 200.00 3.1 OBRAS DE CONCRETO ARMADO EN COLUMNAS 3.1.1 ENCOFRADO Y DESENCOFRADO m² 2,574.65 66.32 170750.788 0.00 3.1.2 ACERO f'y =4200 KG/CM2, GRADO 60 kg 3,748.12 13.89 52061.3868 0.00 3.1.3 CONCRETO F'C= 245 KG/CM2. m³ 376.80 438.72 165309.696 0.00 4.1 OBRAS DE CONCRETO ARMADO EN VIGA 4.1.1 ENCOFRADO Y DESENCOFRADO m² 2,696.60 200546.142 0.00 4.1.2 ACERO f'y =4200 KG/CM2, GRADO 60 kg 3,864.85 14.75 57006.5375 0.00 4.1.3 CONCRETO F'C= 245 KG/CM2. m³ 394.62 457.23 180432.1026 0.00 49.21 74.37 MONTO S/. AVANCE ACTUAL % MET. MONTO S/ % AVANCE ACTUAL MURO DE ALBAÑILERIA CONFINADA m² ASENTADO DE LADRILLO KING KONG 18H APAREJO SOGA m² 548.96 42.54 23352.7584 0.00 ASENTADO DE LADRILLO KING KONG 18H APAREJO CABEZA m² 494.64 51.97 25706.4408 0.00 TARRAJEO EN MUROS m² 1,043.60 23.21 24221.956 0.00 3.1 PUERTA CORTAFUEGO 3.2 INSTALACIONES ELECTRICAS m² 42.00 565.63 23756.46 0.00 TABLERO ELECTRICO METALICO und 153.00 385.62 58999.86 0.00 POZO A TIERRA und 17.00 782.17 13296.89 0.00 PRUEBAS ELECTRICAS glb 20.00 858.12 17162.4 0.00 COSTO DIRECTO GASTOS GENERALES UTILIDAD SUB TOTAL IMPUESTO (IGV) TOTAL PRESUPUESTO CONTRATADO PORCENTAJE DE AVANCE (%) 8.30% 7.30% 1.0000 18.00% 1,891,474.12 156,992.35 138,077.61 2,186,544.08 2,186,544.08 393,577.93 2,580,122.01 100.00% MONTO S/. % AVANCE ACUMUL. SALDO MET. % POR VAL. MONTO 333696.96 100.00 0.00 0.00% 9567.00 333696.96 100.00% 0.00 0.00 204719.81 100.00 0.00 0.00% 7568.20 204719.81 100.00% 0.00 0.00 101629.97 41445.74 90782.00 100.00 100.00 45.99 234.84 0.00 0.00 106596.22 0.00% 0.00% 54.01% 2065.23 3594.60 434.84 101629.97 41445.74 197378.22 100.00% 100.00% 100.00% 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00 0.00 0.00 2024.00 2658.00 189.00 134231.68 36919.62 82918.08 78.61% 70.92% 50.16% 550.65 1090.12 187.80 36519.11 15141.77 82391.62 21.39% 29.08% 49.84% 0.00 0.00 0.00 1689.00 1789.00 205.00 125610.93 26387.75 93732.15 62.63% 46.29% 51.95% 134231.68 36919.62 82918.08 0.00 125610.93 26387.75 93732.15 78.61% 70.92% 50.16% 0.00 0.00 0.00 62.63% 46.29% 51.95% 1007.60 2075.85 189.62 74935.21 30618.79 86699.95 37.37% 53.71% 48.05% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 480.23 365.00 859.00 37.00 20428.98 18969.05 19937.39 20928.31 87.48% 73.79% 82.31% 88.10% 2024.00 2658.00 189.00 0.00 1689.00 1789.00 205.00 0.00 0.00 480.23 365.00 859.00 37.00 20428.98 18969.05 19937.39 20928.31 87.48% 73.79% 82.31% 88.10% 68.73 129.64 184.60 5.00 2923.77 6737.39 4284.57 2828.15 12.52% 26.21% 17.69% 11.90% 0.00 0.00 0.00 0.00 0.00 0.00 138.00 11.00 17.00 53215.56 8603.87 14588.04 90.20% 64.71% 85.00% 138.00 11.00 17.00 53215.56 8603.87 14588.04 90.20% 64.71% 85.00% 15.00 6.00 3.00 5784.30 4693.02 2574.36 9.80% 35.29% 15.00% ARQUITECTURA 3 AVANCE ACUMUL. MET. 772,274.48 64,098.78 56,376.04 892,749.30 892,749.30 160,694.87 1,053,444.17 40.83% 763,067.63 63,334.61 55,703.94 882,106.18 882,106.18 158,779.11 1,040,885.29 40.34% 1,535,342.11 127,433.40 112,079.97 1,774,855.48 1,774,855.48 319,473.99 2,094,329.47 81.17% 356,132.01 29,558.95 25,997.64 411,688.60 411,688.60 74,103.94 485,792.54 18.83% 0.00% 0.00% VALORIZACION MARZO = S/ 1,040,885.29 R=V(K-1) = S/ 10,932.46 VR=V*K = S/ 1,051,817.75 VALORIZACION DE OBRA Nº 04 Mar-22 OBRA : CONTRATISTA : RESIDENTE SUPERVISOR PERIODO MONTO PRESUP. BASE : MONTO CONTRATADO : SISTEMA DE CONTRATACION: : FECHA PRESUP. BASE : FORMA DE EJECUCION: FORMULA Nº 01 - ESTRUCTURAS PRESUPUESTO BASE ITEM DESCRIPCION UND MET. P. UNIT. 1 MOVIMIENTO DE TIERRA 1.1 EXCAV. ZANJAS Y ZAPATAS h=1,50 m. m³ 9,567.00 34.88 1.2 RELLENO CON MATERIAL SELECIONADO m³ 7,568.20 27.05 AVANCE ANTERIOR P. TOTAL MET. 333696.96 9567.00 204719.81 7568.20 101629.9683 2065.23 2 OBRAS DE CONCRETO ARMADO 2.1 OBRAS DE CONCRETO ARMADO EN ZAPATAS 2.1.1 ENCOFRADO Y DESENCOFRADO m² 2,065.23 2.1.2 ACERO f'y =4200 KG/CM2, GRADO 60 kg 3,594.60 11.53 41445.738 3594.60 2.1.3 CONCRETO F'C= 245 KG/CM2. m³ 434.84 453.91 197378.2244 434.84 3.1 OBRAS DE CONCRETO ARMADO EN COLUMNAS 3.1.1 ENCOFRADO Y DESENCOFRADO m² 2,574.65 66.32 170750.788 2024.00 3.1.2 ACERO f'y =4200 KG/CM2, GRADO 60 kg 3,748.12 13.89 52061.3868 2658.00 3.1.3 CONCRETO F'C= 245 KG/CM2. m³ 376.80 438.72 165309.696 189.00 4.1 OBRAS DE CONCRETO ARMADO EN VIGA 4.1.1 ENCOFRADO Y DESENCOFRADO m² 2,696.60 200546.142 1689.00 4.1.2 ACERO f'y =4200 KG/CM2, GRADO 60 kg 3,864.85 14.75 57006.5375 1789.00 4.1.3 CONCRETO F'C= 245 KG/CM2. m³ 394.62 457.23 180432.1026 205.00 42.54 49.21 74.37 MONTO S/. AVANCE ACTUAL % MET. MONTO S/ % AVANCE ACTUAL MURO DE ALBAÑILERIA CONFINADA m² ASENTADO DE LADRILLO KING KONG 18H APAREJO SOGA m² 23352.7584 480.23 ASENTADO DE LADRILLO KING KONG 18H APAREJO CABEZA m² 494.64 51.97 25706.4408 365.00 TARRAJEO EN MUROS m² 1,043.60 23.21 24221.956 859.00 3.1 PUERTA CORTAFUEGO m² 42.00 565.63 23756.46 37.00 3.2 INSTALACIONES ELECTRICAS TABLERO ELECTRICO METALICO und 153.00 385.62 58999.86 138.00 POZO A TIERRA und 17.00 782.17 13296.89 11.00 PRUEBAS ELECTRICAS glb 20.00 858.12 17162.4 17.00 COSTO DIRECTO GASTOS GENERALES UTILIDAD SUB TOTAL IMPUESTO (IGV) TOTAL PRESUPUESTO CONTRATADO 548.96 8.30% 7.30% 1.0000 18.00% PORCENTAJE DE AVANCE (%) 1,891,474.12 156,992.35 138,077.61 2,186,544.08 2,186,544.08 393,577.93 2,580,122.01 100.00% MONTO S/. % AVANCE ACUMUL. SALDO MET. % POR VAL. MONTO 333696.96 100.00 0.00 0.00% 9567.00 333696.96 100.00% 0.00 0.00 204719.81 100.00 0.00 0.00% 7568.20 204719.81 100.00% 0.00 0.00 101629.97 41445.74 197378.22 100.00 100.00 100.00 0.00 0.00 0.00 0.00% 0.00% 0.00% 2065.23 3594.60 434.84 101629.97 41445.74 197378.22 100.00% 100.00% 100.00% 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 0.00% 0.00% 134231.68 36919.62 82918.08 78.61 70.92 50.16 550.65 1090.12 187.80 36519.11 15141.77 82391.62 21.39% 29.08% 49.84% 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 0.00% 0.00% 62.63 46.29 51.95 1007.60 2075.85 189.62 74935.21 30618.79 86699.95 37.37% 53.71% 48.05% 170750.79 52061.39 165309.70 0.00 200546.14 57006.54 180432.10 100.00% 100.00% 100.00% 125610.93 26387.75 93732.15 100.00% 100.00% 100.00% 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 0.00% 0.00% 20428.98 18969.05 19937.39 20928.31 87.48 73.79 82.31 88.10 68.73 129.64 184.60 5.00 2923.77 6737.39 4284.57 2828.15 12.52% 26.21% 17.69% 11.90% 2574.65 3748.12 376.80 0.00 2696.60 3864.85 394.62 0.00 0.00 548.96 494.64 1043.60 42.00 23352.75 25706.44 24221.96 23756.46 100.00% 100.00% 100.00% 100.00% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 53215.56 8603.87 14588.04 90.20 64.71 85.00 15.00 6.00 3.00 5784.30 4693.02 2574.36 9.80% 35.29% 15.00% 153.00 17.00 20.00 58999.86 13296.89 17162.40 100.00% 100.00% 100.00% 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 0.00% 0.00% ARQUITECTURA 3 AVANCE ACUMUL. MET. 1,535,342.11 127,433.40 112,079.97 1,774,855.48 1,774,855.48 319,473.99 2,094,329.47 81.17% 356,132.01 29,558.96 25,997.64 411,688.61 411,688.61 74,103.95 485,792.56 18.83% 1,891,474.12 156,992.35 138,077.61 2,186,544.08 2,186,544.08 393,577.93 2,580,122.01 100.00% VALORIZACION ABRIL = S/ 485,792.56 R=V(K-1) = S/ 5,102.30 VR=V*K = S/ 490,894.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 0.00% 0.00%